top of page

What a Colorado Custom Home Drawing Set Actually Contains

Writer: Barry Shaw
Barry Shaw
5 minutes ago
13 min read

What separates a custom home drawing set that bids clean from one that generates change orders? The answer rarely lives in the renderings. It lives in the sheets: site plan, floor plans, elevations, sections, framing, details, and MEP drawings. Each sheet of a well-organized architectural drawing set answers a specific question a builder, engineer, or plan reviewer will ask in the field.


This post walks through a real BSA custom-home set in order. We will name the one question each sheet answers, from cover sheet to MEP sheets. You will see why a drawing set is a coordination document, not a picture of a house, and why the same house needs different sheets in different Colorado jurisdictions. We will also explain why some sets bid clean while others generate change orders, and how to compare two architects' sets before you sign. At BSA, a licensed architect and contractor work together under one firm, bringing 35 years of local experience in Boulder County, Denver metro, and the Front Range. A free consultation is a low-risk place to start. You will learn to read the set, not just admire the rendering.


A Drawing Set Is a Coordination Document, Not a Picture of a House


Settle those questions on paper and the set bids clean; leave them open and they return as change orders, phone calls, and site visits.


Many homeowners receive a polished rendering they love and no way to tell whether the drawings behind the picture are complete. This walkthrough supplies the missing method: read the set the way the people who build from it do, an approach that reflects how architects reason through a design.


The order of the sheets is not arbitrary. The site plan comes first because every other sheet must fit inside the setbacks. Floor plans and elevations follow because they fix the shape and the skin. Sections, framing, and details come after because they resolve what that shape actually demands. Mechanical, electrical, and plumbing drawings run in parallel and are often required at first review; Greenwood Village asks for MEP schematics with the initial submittal.


Three readers work from the same document. The general contractor prices it, the professional engineer stamps portions of it, and the municipal reviewer approves it. A set that satisfies only one of them is incomplete by definition.


So apply one test to any package you are handed. For each sheet, ask what question it answers. If a sheet cannot answer one, ask why it is in the package. If a question has no sheet, that is the gap that resurfaces during construction.


Which means comparing custom-home architects is really comparing documents. Style varies; the architecture plans drawing package does not. Every firm hands one over, and it is the one deliverable you can read line by line, starting with the cover sheet and index.


The Cover Sheet and Index: What Am I Actually Holding?


Start at page one. The cover sheet answers three questions before anyone reads a line of the drawing: what is this package, who made it, and is it complete? A useful title block carries the project name and address, contact information, a revision block, and an unambiguous label: permit set or construction set.


Turn to the index next. It is the table of contents of the promise. Presented in submittal order, it lets a reviewer confirm at a glance that architectural, structural, mechanical, electrical, and plumbing sheets are present before reading page two. A missing sheet caught at the counter is a delay; caught on site, it is a change order.


The revision block is not decoration. Changes to an approved plan move through a formal revision process, and Pikes Peak's commercial guidance is explicit: resubmittals must include complete revised documents, not single corrected sheets. On residential plans, Pikes Peak Regional Building Department charges $50 per hour for a splice and $100 per submittal after the second submittal, so a clean revision history saves money as well as confusion.


Run this two-minute check:


  • Does the index match the pages in the PDF?

  • Is the project address correct?

  • Is the set clearly marked permit or construction?

  • Does every page carry the same revision number?


A weak package announces itself. Pikes Peak does not accept handwritten red-line changes on master plans and requires options to be clearly identified. Penciled notes and ambiguous alternates tell you the set was assembled casually. The next sheet, the site plan, shows whether that casualness extends to where the house sits.


The Site Plan: Where Is the House Allowed to Sit?


With the index confirmed, the first sheet that does real work is the site plan. It answers one question: on this lot, where may the building sit, and how is that proven to a reviewer? Every later sheet assumes this footprint. Move a wall because a setback was misread, and the floor plans, elevations, framing, and mechanical layout all move with it.


A house shown sitting comfortably inside the lot boundary tells you nothing. A house dimensioned from the building to all four property lines tells the builder and the reviewer the same thing at once. Thornton's architectural review checklist calls for exactly that, including cantilevers and decks in the measurement, plus driveway location, easements, and distances between structures (Thornton architectural review checklist). Most homeowners would not think to check those measurements.


On Colorado sites, grade, slope, runoff direction, solar orientation, roof-plane snow accumulation, utility or septic locations, and defensible space on wildfire-prone land belong on this sheet or in notes beside it. These are the conditions that let a custom home design fit the site rather than fight it. For more context on how local conditions shape drawings, see BSA's architect blog.


Ask three questions of this sheet:


  • Are setbacks dimensioned, not merely drawn?

  • Do decks and cantilevers count in that measurement?

  • Are easements and utility corridors shown on the same page?


If any answer is no, request a revised site plan before pricing begins. The next sheet, the floor plan, takes this approved footprint and asks what happens inside it.


The Floor Plans: What Happens Inside, and What Gets Counted?


Once the footprint is fixed, floor plans answer what happens in each space, how big it is, and what counts toward project area. Thornton requires the structure's square footage and the covered front porch square footage to appear as separate figures, which makes the counting method checkable. Room sizes still have to fit the site, so the lot's slope, soils, and setbacks belong in the same conversation.


A marketing plan shows furniture. A working plan puts dimensions on the walls, draws door and window swings, resolves stair geometry and head clearance, states ceiling heights, places plumbing fixtures where the MEP sheets can serve them, and notes which detail or elevation answers each junction.


Second-story and pop-top plans have to show how the new floor sits on the existing structure, where the stair lands, and what happens to the roof and existing headroom. An ADU needs its own entry, kitchen, bathroom, and separation requirements drawn, not implied.


This sheet locks in room sizes a framer can lay out and a reviewer can measure. Dimensioning plus code compliance separates a sketch from a custom home design document, and both show on the page.


Check two things: are dimensions on the drawing itself rather than only on a furniture layout, and does the square footage note state whether the covered porch and garage are included?


The Elevations: What Does Each Face Look Like, and How Tall Is It?


Read the elevations after the floor plans, because they answer the question the plans leave open: what does each exterior face look like, in what materials, and what is the building height measured against grade? Thornton requires each elevation on its own sheet, with every material labeled, height measured from grade to the highest point, and the design elements the review depends on, such as trim and roof pitch.


Alternates and the dashed line


Anything that changes the exterior, a bay window or a three-car garage, appears on the elevation as a dashed line. The builder learns exactly what changes when a client selects an alternate, and the reviewer sees that the alternate was disclosed rather than slipped in.


This is a documented standard, not a matter of taste. Thornton's checklist requires at least three of nine criteria to differ between models, with window and door placement varying by at least two feet, and it applies a $100 per lot application fee plus $100 per additional elevation.


Elevations lock in more than appearance. They fix the building height and massing that height limits, view corridors, and neighbor objections turn on. They also set the material schedule a contractor prices, and a material note here is a purchasing decision. Since state code now folds wildfire resilience into new construction on wildland-urban-interface land, exterior assemblies belong in this conversation, as our 2026 Colorado resiliency code guide explains.


Confirm the grade line is shown, that height is dimensioned to the highest point rather than just the eave, and that every exterior material called out here appears consistently on the adjacent elevations.


The Sections: What Is Hidden Inside the Wall and Roof Assemblies?


An elevation shows what you see from the street. A section shows what a builder has to build. Homeowners who have studied floor plans and elevations are usually meeting the section for the first time in this conversation, and it is the sheet that answers one question: what is inside the floor, wall, and roof that no exterior view can show?


A section cuts the house open. It reveals assembly layers and insulation, ceiling heights, the roof pitch seen from underneath, foundation depth, and the beam and header conditions the exterior hides.


In Colorado, that is not a technicality. Frost depth and snow load live here, and so do wildfire-resistant assembly choices. The Colorado Model Electric Ready and Solar Ready Code requires construction documents to show roof dead and live load along with the size and location of the solar-ready zone, while counties including Jefferson and Lake are adopting the Colorado Wildfire Resiliency Code on 2026 timelines. Sections also settle passive solar decisions such as overhang depth, which is why passive solar home design starts with roof geometry rather than the windows.


The section locks in relationships that are hard to change later: the roofline against the rooms below it, the exterior wall thickness and therefore the depth of a window, and whether the vaulted ceiling the client pictured actually fits at that height with insulation and structure above it.


Two checks before you accept a set: is there a building section through the whole house and a wall section through a typical exterior wall, and do those sections call out numbered details at the junctions instead of leaving them to the field?


The Framing and Structural Sheets: What Holds the House Up?


Once a section shows what sits inside the assemblies, the framing and structural sheets answer the next question: what carries the load, and who signed off on the parts that must be engineered rather than simply drawn? This is where an architect for custom home work either coordinates with a professional engineer or hands the client a gap.


Shear walls are the panels that keep the house from racking sideways under wind or seismic movement. Durango notes most projects under the International Residential Code include engineered elements such as shear walls, and those elements must be stamped by a professional engineer.


Deferred submittals, items such as truss or sprinkler design approved later in the process, are normal, not a defect. Durango allows items such as truss design and sprinkler design to be listed as deferred. The set should name what is deferred and when it is due, because an unnamed deferred item becomes a surprise during construction.


Framing sheets lock in beam and header sizing, floor and roof framing direction and spacing. An architect can draw a beam at a plausible depth; an engineer confirms that depth with a stamp. That confirmation also informs how design affects cost before bidding.


Look for which sheets carry a professional engineer's stamp, what is listed as a deferred submittal, and whether the framing plan matches the openings shown on the floor plan and the sections.


The Construction Details: How Do the Parts Actually Meet?


The details are where the framing drawings stop being abstract and the pieces have to meet.


At the junctions where buildings leak, crack, or fail, this sheet answers one question: exactly how does one assembly meet another? Details are drawn large enough to instruct, because if the set stays silent, the crew on the scaffold will decide for you. In a Colorado custom home, the usual suspects are roof to wall, deck to house, window and door flashing, foundation to frame, exterior cladding transitions, and the intersection of new construction with existing walls on a remodel or second-story/pop-top addition.


This is where design-build coordination shows up most visibly. A detail has to be buildable by the crew that will stand there. A firm that both draws and builds has to live with its own details, which is one reason the architect and contractor under one roof arrangement changes what gets drawn. The same logic runs through the Colorado custom home design process.


Good details lock in fewer field decisions, fewer substitutions made under time pressure, and a written answer that survives a change of superintendents between design and framing. Test any set two ways: are details numbered and referenced from the plans and sections rather than floating loose at the back, and does it include details for this house's unusual conditions rather than only a generic wall section?



The MEP Sheets: Where Do the Wires, Pipes, and Ducts Go?


Details settle how assemblies meet; MEP sheets settle where the wires, pipes, and ducts live inside them. Mechanical, electrical, and plumbing drawings answer one question: do these systems physically fit, and does the structure leave room? Durango requires MEP drawings to start initial review, which is the practical answer to why a house needs mechanical drawings at all.


For a homeowner, the value is concrete: plumbing fixtures that match the floor plan, a panel location and capacity that can carry the house, a clear path for conditioned air, a defined spot for the water heater, and a range hood that can vent outside from where the range sits. Coordination failures show up here first. A steel beam can sit exactly where a duct needs to run, a vanity can lack a drain path through the framing, or a mechanical closet can be drawn too small for its equipment. These are hypothetical examples of clashes that appear only when MEP sheets are laid over structural drawings.


Colorado code direction raises the stakes. Colorado has mandated that new construction be designed to satisfy the Model Electric Ready and Solar Ready Code, so electrical design now carries panel and circuit requirements older sets may not show. Our Colorado's 2026 carbon code explains what that means for custom home design.


Before you compare sets, check three things: MEP sheets are in the initial submittal, not deferred entirely; equipment locations are drawn, not just described; and plumbing fixture locations match the rooms on the floor plan.


Why the Same House Needs Different Sheets in Different Colorado Jurisdictions


Even a complete MEP package does not make a drawing set portable. Two firms can hand over different sets for a similar house because the authority having jurisdiction sets part of the requirement. Boulder County, the Denver metro, and mountain communities do not ask the same things.


The range is documented. Thornton publishes an architectural review checklist covering dimensioned site plans, elevation labeling, and facade variation. Durango specifies title block contents, sheet index order, MEP at first review, and permitted deferred submittals. Pikes Peak publishes a residential guide covering who may prepare plans, master plan fees, splice charges, and resubmittal charges.


Code editions differ too. Pikes Peak lists the 2021 International Residential Code and the 2021 International Energy Conservation Code alongside its 2023 regional code, so a set prepared for one city is not automatically ready for another.


Plan preparer rules matter to the client. Pikes Peak allows plans prepared by a homeowner pulling their own permit, by a Colorado-licensed design professional, or by a contractor holding a Building Contractor C license or higher. Which of those prepared your set determines what it can and cannot contain.


This is where local experience shows up in a custom home design set: knowing which department reviews your address, which checklist applies, and which local amendments add requirements before the drawings are finished rather than after the first rejection.


Why Some Sets Bid Clean and Others Generate Change Orders


Jurisdiction explains part of the variation between Colorado sets. Gaps explain the expensive part. Change orders often begin as questions the drawings did not answer. A contractor bidding a set with gaps rarely stops to ask. The contractor prices an assumption or adds a contingency, and that assumption gets revisited once demolition or site work begins.


The gaps that recur are the ones the earlier sheets were meant to close. Contractors can only price what they can see. Two bids built on different assumptions are not comparable even when totals look close. A complete set narrows that spread, which is the practical reason homeowners should care about drawing completeness. A complete, correctly labeled package is also the less expensive path through permitting. Pikes Peak Regional Building Department charges $100 per submittal after the second submittal and $50 per hour for a splice to an approved plan.


No set eliminates every field question. Site conditions vary, and clients make selections mid-project. A good set makes the remaining questions specific, written, and priced rather than improvised.


How to Compare Two Architects' Drawing Sets Before You Sign


Completeness is the variable you can test before signing. Ask both firms for the same checklist and compare line by line:


  • Cover sheet with title block and revision block

  • Sheet index in submittal order

  • Site plan with dimensioned setbacks to all four property lines

  • Dimensioned floor plans with square footage

  • Elevation sheet per exposed face, with labeled materials and height

  • Building and wall sections

  • Framing and structural sheets with engineer stamps where required

  • Numbered construction details

  • MEP drawings


Then ask what each permit set includes and what it lists as deferred. Two sets can look equally polished as renderings and differ enormously as documents; the deferred list makes that difference visible first.


Ask who prepares the drawings, who stamps engineered elements, and whether the same people who draw the house stay involved once construction begins. That answer tells you how much field translation you should expect to do yourself.


Ask how revisions are handled, whether the set will be labeled permit set or construction set, and how the firm tracks local code editions and jurisdiction checklists for your address.


Finally, confirm the entry point. A preliminary design and estimate gives you something concrete to put in front of contractors for bids, so ask whether an initial consultation and that preliminary step are offered before a full contract is discussed.


Conclusion: Read the Set, Not the Rendering


Before you compare two proposals side by side, ask each firm for its sheet index. It costs nothing to request, and it is the table of contents of what the firm is actually promising to deliver. Then walk the set in order, asking what question each sheet answers: are setbacks dimensioned to all four property lines, is each elevation labeled with materials and height, do sections cut through the assemblies, does framing carry engineer stamps where required, are details numbered, and is MEP included at first submittal?


Next, ask what is deferred, who stamps the engineered elements, and how revisions are handled. Those three answers quickly separate a working document from a presentation package. Treat the drawing set as the deliverable you are buying when you hire a custom-home architect, and judge it as a coordination document. At Louisville-based BSA Inc. Design & Construction, that coordination is built in: the founder is both a licensed architect and a general contractor, the firm brings 35 years of combined design and construction experience, and it offers a free initial consultation with a preliminary design and estimate to put in front of bidders.